Matters needing attention in PE drainage pipe construction
Release Time:
Jun 30,2022
1. Before installing the pipe: Carefully check whether there is any damage in the process of loading, unloading, transportation and stacking. If any defective pipes such as damaged cracks and deformation are found, they should be removed in time. 2. Inspection well and pipeline connection: The flexible joint sealed with flexible packing should be adopted, and the specific structure shall be carried out according to the design requirements. 3. When excavating trenches and making foundations, attention should be paid to: (1) The net width of the groove bottom should be used according to the outer diameter of the pipe plus 0.6m; (2) Drainage measures should be taken during trench excavation to prevent the bottom of the trench from being soaked in water;
1. Before installing the pipe:
Carefully check whether there is any damage in the process of loading, unloading, transportation and stacking. If any defective pipes such as damaged cracks and deformation are found, they should be removed in time.
2. Inspection well and pipeline connection:
The flexible joint sealed with flexible packing should be adopted, and the specific structure shall be carried out according to the design requirements.
3. When excavating trenches and making foundations, attention should be paid to:
(1) The net width of the groove bottom should be used according to the outer diameter of the pipe plus 0.6m;
(2) Drainage measures should be taken during trench excavation to prevent the bottom of the trench from being soaked in water;